Press release from the City of Knoxville - Blog:
May 5, 2022
The Amherst Road Slope Stabilization Project was complicated: The slope banking the roadway and shoulder was deteriorating, and the road was slowly getting skinnier as outer pieces of asphalt crumbled.
The solution involved bringing in better soils, stone and gabion baskets. And the upgrades – re-establishing the roadway shoulder and bringing the guardrails up to current standards – required the cooperation of residential property owners on one side and the CSX railroad line on the other side.
So on April 1, following a City investment of roughly $1.6 million, this large section of Amherst Road – closed since last fall – was reopened to commuters.
A 775-foot-long stretch of slope is now stabilized, reinforced with a 533-foot-long retaining wall. New guardrails have been installed. The project also corrected an issue with asphalt settlement at the Amherst Road bridge over the rail line near Lee Road.
Poor soils were discovered as the wall was being constructed, resulting in the need for additional gabion baskets.
CDM Smith was the project designer, and Morgan Contracting was the construction contractor.
This press release was produced by the City of Knoxville - Blog. The views expressed here are the author's own.