Description
Press release from the South Pasadena Unified School District:
August 7, 2020
South Pasadena High School - Athletics Project
Final grading is ongoing for the site and we are installing the perimeter fencing and amending the planter soils in preparation for final planting. The remainder of the sitework concrete, site lighting, tennis courts and basketball courts are scheduled towards the end of the month.
We are installing the final finishes in the gymnasium building; lighting and HVAC has been installed and currently operational as we condition the building interior. All roofing materials and equipment are complete with the final roof coating scheduled shortly.
Additionally, final painting inside the gymnasium is currently ongoing. The wood flooring in the main gymnasium is currently being installed with the final sanding, striping and sealingscheduled at the end of August. It is anticipated that the wood flooring in the practice gym will also be completed on a similar schedule.
As the final crowning piece, we anticipate installing the "Roosevelt" main entry signage in the last week of the projectm upon completion of the mainentry decorative concrete
Attached Files SPUSD Community Newsletter - SPHS Athletics Project - AUG 2020.pdf This press release was produced by the South Pasadena Unified School District. The views expressed here are the author's own.
Discussion
By posting you agree to the Terms and Privacy Policy.