MOKENA, IL — At its Monday meeting, the Mokena Village Board awarded a $177,812 contract for the storm sewer improvement project on Hummingbird Lane.
Copenhaver Construction was awarded the contract for the project, which will include replacing 660 linear feet of storm sewer pipe in the backyards of properties along Hummingbird Lane, board documents state.
Dan Peloquin, Civil Engineer for the Village, said Copenhaver has done projects for the Village in the past and also submitted references for this type of work.
$200,000 was budgeted for the project, so Copenhaver's bid amount is $22,188 below budget, according to board documents.
For more news and information like this, subscribe to the Mokena Patch for free. If you have an iPhone, click here to get the free Patch iPhone app; download the free Patch Android app here. Don't forget to like us on Facebook!