Rustcraft Rd Sewer Improvements Project In Dedham - Work Schedule For Week Of September 7

News

Dedham MA

07 September, 2020

9:23 AM

Description

Press release from the Town of Dedham: September 5, 2020 To date, RJV has installed approximately 3,500 LF (approx 71% of the total 4,885 LF to be installed) of the 10" Ductile Iron Force Main. For the week of September 7th, RJV Construction Corp. (Contractor) will be performing the following activities: Construction will not take place on Monday, 9/7 in observance of Labor Day. Excavation for and installation of the 10" force main continuing near Station 14+00 to Station 9+00. Police details will be present to direct traffic around the work area. For up-to-date information and photos regarding this project, please be sure to subscribe to Engineering Project Updates by clicking here. You can download a copy of a map showing the project limits and/or construction plans at the Engineering Department's Rustcraft Road Sewer Improvements Project page by clicking here. This press release was produced by the Town of Dedham. The views expressed here are the author's own.

By:  view source

Discussion

By posting you agree to the Terms and Privacy Policy.

/
Search this area