Maskwonicut Street Bridge 100% Plans Now Available In Town Of Sharon

News

Sharon MA

17 November, 2021

9:45 PM

Description

Press release from the Town of Sharon: November 16, 2021 Maskwonicut Street Bridge notice to proceed date is 10/24/2021. Construction would begin in Spring of 2022. The anticipated completion date is August 31, 2024. The MassDOT Project Manager, Stephen Soma, should receive all comments on the Maskwonicut Street bridge project. Please CC Town Engineer, Peter O'Cain, on your e-mail at [email protected], so he can verify that your comments are being answered. Mr. Soma can be reached by e-mail at [email protected] Final Approved Design Plans: Maskwonicut Street Bridge This press release was produced by the Town of Sharon. The views expressed here are the author's own.

By:  view source

Discussion

By posting you agree to the Terms and Privacy Policy.

/
Search this area