Yardwork to create pad for above ground pool:
Please quote your price for doing this work.
I need you to move some railroad ties placed level in my yard to make a better grade level platform for my kid’s above ground pool for next season.
I have a drawing showing the work.
Here is a description of the work:
Slice existing lawn sod: Cut slices in existing sod 4” deep: 40 lineal feet. Remove for reuse 80 square feet of sod. Relocate and place cut sod 20’ away to new bare soil location.
Excavate trenches for new railroad tie timbers. Trenches across yard 8” deep x 12” wide. 48 lineal feet long. Place excavated soil on tarp next to trench for reuse.
Remove existing railroad tie timbers that are set level in soil for reuse. 48 lineal feet
Set removed Railroad Ties into new trenches: 48 lineal feet of ties to be placed level to surrounding yard. Backfill salvaged soil into gaps beside railroad ties, for level surface.
Place remaining soil into removed railroad tie trenches.