Description
AGOURA HILLS, CA — Pavement rehabilitation construction will cause traffic delays through Wednesday, according to the City of Agoura Hills.
All American Asphalt had to push Monday's scheduled construction due to mechanical issues at their asphalt plant. On Tuesday, construction will close all but one lane of traffic on Emerson Court, Deerview Court, Heather Court, Oakvista Court and Woodbrook Drive.
On Wednesday, construction will close all but one lane of traffic on Dunegal Court, Modena Place and Rainbow Crest Drive.
Due to a mechanical issue at the asphalt plant, All American Asphalt was not able to pave streets on Monday. The revised paving schedule is as follows: Tuesday, September 28th Emerson Ct. Deerview Ct. Heather Ct. Oakvista Ct. Woodbrook Dr.— City of Agoura Hills (@CityAgouraHills) September 28, 2021 Pavement restoration began at the intersection of Agoura Road and Liberty Canyon Road on Sept. 22.
Discussion