Here is the scope of the job:
PLUMBING (EXT. SEWER & WATER
Install (N) 4” Sewer lateral from (E) primary house sewer to the ADU
Trench is dug
install back flow device
Install clean-out @ ADU entrance
Install 1-1/4” copper from (E) primary house water line to ADU
Underground fittings to be brazed
1-1/4” straight Copper pipe type K is supplied
Install Shutoff @ entrance
Install Moen Flo device @ entrance (supplied)
GAS PLUMBING
Install Gas line from (E) meter location to ADU entrance
Install Shutoff valve @ ADU Entrance
Complete iron pipe install from (E) 1 -1/2” iron pipe to Furnace location (~10 feet)
install shutoff and dripleg for furnace as required
Complete iron pipe install to on-demand water heater location (~4 feet)
install shutoff and dripleg for water heater as required
When PGE installs Gas Meter #2:
Connect gas line to meter #2
Install Earthquake device/s per PGE req. @ meters