I need a 4 man concrete crew, one man or 4 men. We will lay 1,904 s.f. concrete pad 34'x56', plus a 150 sf and 100 sf entrance way for a total of 2154 s.f., 4" thick for the inside of a pole barn. The inside of the pole barn has a 2x8 skirt at the bottom which acts as the form. I will pay for concrete, do the site prep. I will buy fiber reinforced concrete, so no wire or rebar to slow you down. I do all the forms.
All you do is pour and finish, then cut expansion joints 8' square. Labor only. I can rent all the tools
The work can be divided into three sections if preferred, so that each lay is 11.33 feet wide and 56' long. This provides for screeding with a 2x4x 14'. This also permits the work to be divided into three different days, which can be three different weekends for those that want a side gig for a weekend. I figure a 4 man crew with two screeding, two pulling concrete, and me moving concrete from the truck with a buggy.