Description

Press release from the City of Greenbelt: 08/02/2021 2:56 PM Schedule work for Milling and Patching (if weather permits)   1. Lakeside Drive - from Lakecrest Drive to Maplewood Court August 9, 10, & 11 2. Ridge Road - from Southway to 1 Court Ridge    August 12, 13, 17, 19 & 20  3. Crescent Road -  from 1 Court Crescent to Lakeside Drive    August 23 & 24  4. Northway -  from Hillside to Ridge Road    August 25 & 26  If the milling & patching is done as planned without any delays, paving of streets will begin around August 30th (weather dependent). This press release was produced by the City of Greenbelt. The views expressed here are the author's own.