Press release from the Village of Lindenhurst: May 4, 2021 The John Street Roadwork Project is advancing as planned. Work has progressed as follows: Milling was completed on Friday 4/30/21. Crack sealing started on Monday 5/3/21. Full depth asphalt repairs of localized deteriorated areas started on Monday 5/3/21. Final Paving will begin once full depth areas are completed. It is anticipated that paving will begin next week. This press release was produced by the Village of Lindenhurst. The views expressed here are the author's own.