Press release from the Village of Menomonee Falls:
August 13, 2020
If weather conditions don't change the schedule, the night work at the intersection will proceed as follows:
Thursday, August 20th from 9:00 pm – 5:30 am Friday, August 21st from 9:00 pm – 5:30 am Saturday, August 22nd from 9:00 pm – 5:30 am The intent is a full road closure in all directions during the night work with reopening by 6:00 am the following mornings. This aim of this plan is to alleviate the worst traffic congestion by completing the work over three nights when traffic volumes are typically lower.
This press release was produced by the Village of Menomonee Falls. The views expressed here are the author's own.