We are a local Pool contractor that needs to sub out a pool finish job on a small pool. We provide all materials and use Pebble-tec Finishes only. YOU MUST BE AN EXPERIENCED TEAM. We are looking for a team that usually does this that is looking to make extra money on the side. This whole job will need a team of 3 people and pay for all 3 people total. We have already drained and unplugged the pool. The steps followed will be :
a. Pressure wash pool to remove loose material
b. Check for and Hammer out all hollow spots in the pool. Hand held jack hammer maybe needed for some spots
c. Suck up all Debris and then apply Bond Kote. You must have a mixing drill and buckets. Let cure for 24 hours.
d. Mix and apply Pebble-tec finish. You must have one person mixing at all times. Apply one inch coat around entire pool
e. Apply 20 gallons of muriatic acid to every portion of the pool. And wash down afterwards
Those are the steps, if you are an experienced team you will know the additional things we purposely left out. This job pays an experienced team $1000 total for all 3 people. So you divide that up yourself. You must have your own tools. You get paid upon completion. This usually takes a team of 3, two whole days to complete.